Ocean Farm 1 tow and marine operations

Ocean Farm 1 was scheduled for upgrade work at Aker Verdal, requiring the large floating fish farm to be disconnected from its offshore location at Frohavet and safely transported to the yard.
Marine operations had to cover the complete transition from the offshore location to inshore mooring, followed by the return operation after the upgrade.
Draft and clearance required careful planning especially in the high-traffic channels of Trondheimsfjord. To avoid hull stress and drift of the structure, the weather window was limited.
Working with partners in the Windstaller Alliance, Aker Solutions provided project management and marine operations planning, including engineering and procurement support.
The marine scope covered hook-down, tow to shore and inshore mooring, followed by the subsequent tow-out and hook-up of Ocean Farm 1. Aker Solutions also provided asset management related to the marine operations.
Ocean Farm 1 was successfully transported to Aker Verdal for upgrade work and subsequently returned to Frohavet for its next production cycle.
The project demonstrated how offshore marine operations expertise can be applied beyond traditional energy projects to large floating aquaculture infrastructure.